Milestones Status Report
REPORT ON THE STATUS OF MILESTONES IN SUBMISSION/APPROVAL/DEDICATION PROCESS
Last updated: 20 November 2024
This ongoing report shows the status of Milestones and Special Citations in the various stages of the process, updated frequently by IEEE History Center staff. Milestones and Special Citations are listed with their docket numbers. The IEEE Region and the sponsoring organizational unit are shown in parentheses. Please note the titles given here are shortened or working titles, not the full or official titles. While in the approval process, proposals have a History Committee advocate assigned to them, whose initials are given in brackets.
To see a count of how many IEEE Milestones have been dedicated, click List of Milestones by year dedicated
For a list of dedicated Milestones in chronological order by date of achievement, see Chronological List of Milestones
To see how many Milestones have been dedicated in each Region and Section, see List of Dedicated Milestones by Region
Interested in proposing a milestone? Any IEEE member can submit a milestone proposal. Here is a list of important achievements suitable for proposal, and which we encourage a proposer to consult the Milestones Guidelines and submit. This list is not exclusive; if you know of other achievements you wish to submit, you are welcome to do so.
CONTENTS:
Section A. Proposals Needing Advocates
Section B.1 Proposals Being Written and Awaiting Completion and Submission
Section C.1 Proposals Proposals Submitted, Awaiting Independent Expert Reviews
Section C.2 Proposals Reviews Received, Awaiting Advocate Decision
Section D.1 Proposals Approved by Advocate and Awaiting Milestones Subcommittee Chair Approval
Section D.2 Proposals Approved by Advocate and Awaiting Citation Approval
Section D.3 Proposals Awaiting Name-in-Citation Approval from Milestones Subcommittee
Section D.4 Proposals Awaiting Further Development or evaluation from Milestones Subcommittee
Section D.5 Proposals Awaiting History Committee Action
Section E Proposals Approved by History Committee and Awaiting Board of Directors Action
Section F Milestones Approved by Board of Directors and the Dedication Ceremonies Are Being Planned
Section G Milestones Dedicated
++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
A. PROPOSAL AWAITING APPOINTMENT OF ADVOCATES BY MILESTONES SUBCOMMITTEE CHAIR:
Proposals with a personal name in the citation are indicated by (*)
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Plaque payment commitment received? | Full text of references received? | 4 Possible Independent Expert Reviewers Suggested? | |
2023-02 | Acoustical Labyrinth | ADVOCATE NEEDED | Region 1 | Rochester Section | |||||||
2023-15 | Bayer Color Filter Array | ADVOCATE NEEDED | Region 1 | Rochester Section | |||||||
2023-21 | URUPAC, 1977 | ADVOCATE NEEDED | Region 9 | Uruguay Section | 3 August 2024 | yes | yes | yes | yes | yes | |
2024-01 | Discovery of Photoelectrets | ADVOCATE NEEDED | Region 8 | Bulgaria Section | |||||||
2024-02 | Optical Tweezers | ADVOCATE NEEDED | Region 1 | North Jersey Section, Photonics Society | yes | yes | yes | ||||
2024-04 | Radio Astronomy | ADVOCATE NEEDED | Region 1 | New Jersey Coast Section IM/C Chapter | |||||||
2024-08 | Digital TV Standards Converter | ADVOCATE NEEDED | Region 10 | Tokyo Section | |||||||
2024-09 | Super Resolved Microscopy, 1992(*) | ADVOCATE NEEDED | Region 1 | North Jersey Section | |||||||
2024-10 | Quantum Dots, 1983(*) | ADVOCATE NEEDED | Region 1 | North Jersey Section | 18 November 2024 | yes | yes | yes | yes | yes | |
2024-12 | Charge Coupled Device Digital Camera, 1970-1974 | ADVOCATE NEEDED | Region 1 | North Jersey Section | yes | yes | yes | ||||
2024-13 | Fractional Quantum Hall Effect, 1982(*) | ADVOCATE NEEDED | Region 1 | North Jersey Section | yes | yes | yes | ||||
2024-14 | Molecular Beam Epitaxy, 1973-1978 | ADVOCATE NEEDED | Region 1 | North Jersey Section | yes | yes | yes | yes | yes | ||
2024-20 | Discovery of Interstellar Carbon Monoxide, 1970 | ADVOCATE NEEDED | Region 6 | IEEE Tucson Section | |||||||
2024-27 | First Application of Digital Computing to Business Processes, 1951 | ADVOCATE NEEDED | Region 8 | IEEE UKRI Section | yes | ||||||
2024-28 | Orbital X-Band Real Aperture Side-Looking Radar of Cosmos-1500 | ADVOCATE NEEDED | Region 8 | IEEE Ukraine Section | yes | ||||||
2024-31 | Datapoint 2200 Personal Computer, 1970 | ADVOCATE NEEDED | Region | Section |
Advocates must be either current IEEE History Committee members, past IEEE History Committee members, or past proposers or expert reviewers of successful milestone proposals. In March 2024, the History Committee voted that past proposers and expert reviewers of successfully-dedicated Milestone proposals are also eligible to serve as milestones advocates, subject both to having completed proposer/advocate training, and receiving Milestones Subcommittee Chair’s approval. To volunteer to serve as an advocate, contact the IEEE History Staff milestone administrator at ieee-history@ieee.org
B. STATUS
B.1 PROPOSALS BEING WRITTEN AND AWAITING COMPLETION AND SUBMISSION BY PROPOSERS
In the case of inactive Proposals, i.e. proposals which are incomplete or have had no new material added to them for a period of a year, the advocate will email the proposer(s) to advise that the proposal will be deleted from the Milestones Status Report unless there is activity within the next month.
Proposals with a personal name in the citation are indicated by (*)
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Plaque payment commitment received? | Full text of references received? | 4 Possible Independent Expert Reviewers Suggested? |
2011-01 | Discovery of High Temperature Superconductivity, 1986 (*) | JnMz | Region 8 | IEEE Switzerland Section | yes | yes | yes | |||
2014-08 | Hollow dielectric beam waveguide, 1966 (*) | AlMr | 8 | Ukraine Section | ||||||
2015-07 | Space Shuttle Remote Manipulator | JhVr | 7 | Toronto | yes | yes | yes | yes | ||
2016-01 | Disconnectable Cable Terminating Device, 1905 | JaMg | 5 | Chicago | ||||||
2017-12 | Apollo Unified S-Band Communications Systems | DvMc | Region 6 | Scottsdale Arizona Section | ||||||
2020-10 | Mechanicville Hydroelectric Facility, 1898 (*) | PiKe | Region 1 | Schenectady Section | yes | |||||
2021-02 | Field Programmable Gate Array | BBrg | Region 6 | Santa Clara Valley Section | yes | yes | ||||
2021-07 | Intermodal Transportation System, 1991 | PiKe | Region 2 | Washington DC Section/Vehicular Tech. Soc. | ||||||
2021-17 | Spread Spectrum Communication | MrHn | Region TBD | Section TBD | ||||||
2021-18 | Marconi's Yacht Elettra (*) | ErTj | Region 8 | Italy Section | ||||||
2022-06 | Electronic Lavatory Washlet, 1980 | MxCh | Region 10 | Fukuoka Section | ||||||
2022-13 | Longley-Rice Terrain Model | MtSl | Region 5 | IEEE Denver Section | yes | yes | yes | yes | ||
2022-14 | Special Citation: AT&T History Museum | SrPo | Region 1 | New Jersey Coast Section | yes | |||||
2022-20 | Development of Optical Image Stabilizer | ClSa | Region 10 | Kansai Section | yes | yes | ||||
2022-21 | Small Electronic Calculating Machine, 1948-1951 | StSe | Region 8 | Ukraine Section | ||||||
2022-23 | Theory of Superconductivity, 1957 | DvMc | Region 4 | Central Illinois Section | yes | |||||
2023-04 | Instantaneous Reactive Power in Three-Phase Circuits (*) | IvPc | Region 10 | Tokyo Section | ||||||
2023-12 | Digital Radiography | DvBr | Region 1 | Rochester Section | ||||||
2023-14 | Commercial 800 MHz Analog Cellular | DvMc | Region 10 | Tokyo Section | ||||||
2023-17 | DOCSIS, 1997 | KiMo | Region 5 | Denver Section | yes | yes | ||||
2023-23 | Image Stabilizer, 1981-1988 | ClSa | Region 10 | Kansai Section | yes | |||||
2023-26 | Discrete Cosine Transform | ClSa | Region | Section ?, Signal Processing Society | ||||||
2023-27 | Edith Clarke achievements | ClSa | Region 1 | Section ? | yes | |||||
2024-02 | Optical Tweezers | ADVOCATE NEEDED | Region 1 | New Jersey Coast Section, Photonics Society | yes | yes | yes | |||
2024-03 | Colossus Mark 1, 1944 | BBrg | Region 8 | UKI Section | yes | yes | yes | |||
2024-05 | Microwave Oven | MxCh | Region 1 | Boston Section | ||||||
2024-09 | Super Resolved Microscopy, 1992(*) | ADVOCATE NEEDED | Region 1 | North Jersey Section | yes | yes | ||||
2024-12 | Charge Coupled Device Digital Camera, 1970-1974 | ADVOCATE NEEDED | Region 1 | North Jersey Section | yes | yes | ||||
2024-13 | Fractional Quantum Hall Effect, 1982(*) | ADVOCATE NEEDED | Region 1 | North Jersey Section | yes | yes | ||||
2024-14 | Molecular Beam Epitaxy, 1973-1978 | ADVOCATE NEEDED | Region 1 | North Jersey Section | yes | yes | yes | yes | yes | |
2024-15 | Theories on Neural Networks | MtSl | Region 1 | North Jersey Section | yes | yes | yes | yes | yes | |
2024-17 | Invention of Deep Learning, 1965 | ClSa | Region 8 | Ukraine Section | ||||||
2024-19 | Usuda Deep Space Center, 1984 | SrPo | Region 10 | IEEE Tokyo Section | yes | |||||
2024-20 | Discovery of Interstellar Carbon Monoxide, 1970 | ADVOCATE NEEDED | Region 6 | IEEE Tucson Section | ||||||
2024-24 | Linux-Based Supercomputing | BBrg | Region 6 | IEEE Albuquerque Section | yes | yes | yes | yes | yes | |
2024-28 | Orbital X-Band Real Aperture Side-Looking Radar of Cosmos-1500 | ADVOCATE NEEDED | Region 8 | IEEE Ukraine Section | yes | |||||
2024-29 | Augmented Reality for Live Sports Broadcast, | KiMo | Region 6 | Santa Clara Valley | yes | yes | yes | yes | yes | |
2024-30 | First U.S. Long-Distance Commercial Electric Power Transmission, 1889 | RbDn | Region 6 | IEEE Oregon Section | yes | yes |
C. UNDER ADVOCATE AND/OR INDEPENDENT EXPERT REVIEW
C.1. PROPOSALS SUBMITTED AND AWAITING INDEPENDENT EXPERT REVIEWS
Advocates shall complete the review of milestone proposals within six months of submission of the proposal, except in cases where an unusual circumstance or major obstacle arises. Within 2 months, advocate works with proposers to select independent expert reviewers and to make sure all materials submitted are complete; within 4 months, advocate receives expert reviews; within 6 months, advocate completes review and recommends History Committee action.
Advocates please notify History Center Staff Milestones Administrator when reviews have been received.
Proposals whose reviews or advocate decision are overdue will show their docket numbers in red.
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 possible Independent Expert Reviewers suggested? | Expert Reviewers chosen due date | Reviews due | Advocate recomm due |
2021-08 | Commercialization of Rice Cookers, 1923 | PiKe | Region 10 | Tokyo Section | 30 July 2021 | yes | yes | yes | 30 September 2021 | 30 November 2021 | 30 January 2022 | ||
2021-15 | Okumura Curve and Commercial Cellular Telephone System (*) | DvMc | Region 10 | Tokyo Section | 28 September 2021 | yes | yes | yes | yes | 28 November 2021 | 28 January 2022 | 28 March 2022 | |
2022-01 | Commercially Successful CRT for Television (*) | SeSl | Region 1 | North Jersey Section | 4 November 2022 | yes | yes | yes | yes | 4 January 2023 | 4 March 2023 | 4 May 2023 | |
2022-02 | First Live Commercial Trans-Atlantic Radio Broadcast | DvBr | Region 1 | IEEE Maine Section | 6 December 2023 | yes | yes | yes | yes | 6 February 2023 | 6 April 2023 | 6 June 2023 | |
2022-07 | Semiconductor Quantum-Well Laser Diode, 1977 (*) | DvBr | Region 4 | Central Illinois Section | 3 September 2022 | yes | yes | yes | yes | 3 November 2022 | 3 January 2023 | 3 March 2023 | |
2023-07 | Unipolar conduction of metal semiconductor junctions | IvPc | Region 10 | Germany Section | 1 December 2023 | yes | yes | yes | yes | 1 February 2024 | 1 April 2024 | 1 June 2024 | |
2023-10 | p-q Theory of Three-Phase Instantaneous Real and Imaginary Powers, 1983-1986 | IvPc | Region 10 | Tokyo Section | 21 June 2023 | yes | yes | yes | yes | 21 August 2023 | 21 October 2023 | 21 October 2023 | |
2023-11 | ALCOR Radar | GlCo | Region 1 | Boston Section | 12 March 2024 | yes | yes | yes | yes | yes | 12 May 2024 | 12 July 2024 | 12 September 2024 |
2023-13 | Sidrapong Hydel Power Station | ClSa | Region 10 | Kolkata Section | 11 November 2024 | yes | yes | yes | yes | yes | 11 January 2025 | 11 March 2025 | 11 May 2025 |
2023-16 | Engineering Data Analysis System sNOVA, 1989-1997 | JnMz | Region 10 | Taipei Section | 27 July 2023 | yes | yes | yes | yes | 27 September 2023 | 27 November 2023 | 27 January 2023 | |
2023-21 | URUPAC, 1977 | ADVOCATE NEEDED | Region 9 | Uruguay Section | 3 August 2024 | yes | yes | yes | yes | yes | 3 October 2024 | 3 December 2024 | 3 February 2024 |
2024-07 | JUNET, 1984 | TmHs | Region 10 | Tokyo Section | 15 April 2024 | yes | yes | yes | yes | yes | 15 June 2024 | 15 August 2024 | 15 October 2024 |
2024-10 | Quantum Dots, 1983(*) | ADVOCATE NEEDED | Region 1 | North Jersey Section | 18 November 2024 | yes | yes | yes | yes | yes | 18 January 2025 | 18 March 2025 | 18 May 2025 |
2024-18 | Northern Cross Radio Telescope | DvMc | Region 8 | Italy Section | 25 September 2024 | yes | yes | yes | yes | yes | 25 November 2024 | 25 January 2025 | 25 March 2025 |
2024-23 | Deutsches Museum special citation | SrPo | Region 8 | IEEE Germany section | 29 August 2024 | yes | yes | yes | yes | yes | 29 October 2024 | 29 December 2024 | 1 March 2025 |
Proposals with a personal name in the citation are indicated by (*)
C.2. PROPOSALS WITH INDEPENDENT EXPERT REVIEWS RECEIVED AND AWAITING ADVOCATE DECISION
Advocates shall complete the review of milestone proposals within six months of submission of the proposal, except in cases where an unusual circumstance or major obstacle arises. Within 2 months, advocate works with proposers to select independent expert reviewers and to make sure all materials submitted are complete; within 4 months, advocate receives expert reviews; within 6 months, advocate completes review and recommends History Committee action.
Proposals whose reviews or advocate decision are overdue will show their docket numbers in red.
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 Independent Expert Reviewers suggested? | Independent Expert Reviewers chosen due date | Reviews due | Advocate recomm due |
D. BEING FINALIZED FOR, OR EXPECTING, HISTORY COMMITTEE ACTION
D.1. PROPOSALS APPROVED BY ADVOCATES AND AWAITING APPROVAL BY MILESTONES SUBCOMMITTEE CHAIR
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 Independent Expert Reviewers suggested? |
D.2. PROPOSALS APPROVED BY ADVOCATES AND AWAITING FINALIZED CITATIONS APPROVAL FROM PROPOSERS
Once the proposers have agreed to the wording, the proposals will be submitted to the History Committee for action. If there is a name in the citation, the proposal will be submitted to the Milestones Subcommittee for pre-approval.
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 Independent Expert Reviewers suggested? |
D.3 PROPOSALS AWAITING NAME-IN-CITATIONS APPROVAL BY MILESTONES SUBCOMMITTEE
Next Milestones Subcommittee meeting/teleconference: TBD. If inclusion of name is approved, the proposals will be submitted to the History Committee for action
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 independent Expert Reviewers Suggested? |
D.4 PROPOSALS AWAITING FURTHER DEVELOPMENT OR EVALUATION, EITHER BY MILESTONES SUBCOMMITTEE OR HISTORY COMMITTEE
Proposals in this section are being worked on by the Milestones Subcommittee with an eye to recommending improvements to the proposer(s)
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 Independent Expert Reviewers suggested? |
2021-12 | Variational Reaction Theory for Finite Element Formulation, 1979-1991 | JnMz | Region 10 | Taipei Section | 26 April 2022 | yes | yes | yes | yes | |
2022-16 | MARS-1 Railroad Reservation System, 1959 | JnMz | Region 10 | Tokyo Section | 28 October 2022 | yes | yes | yes | yes |
D.5. PROPOSALS AWAITING HISTORY COMMITTEE ACTION
The proposals are expected to be acted upon at the next History Committee meeting or teleconference
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 Independent Expert Reviewers suggested? |
2021-04 | ADSL:Expediting Broadband Internet Access for society, 1993-1997 | ClSa | Region 8 | Benelux Section | 16 April 2021 | yes | yes | yes | yes | yes |
2022-11 | Vertical Cavity Surface-Emitting Laser, 1977 (*) | JaMg | Region 10 | Tokyo Section | 16 August 2024 | yes | yes | yes | yes | yes |
2023-22 | Silica-Based Arrayed Waveguide | SeSl | Region 10 | Tokyo Section | 1 February 2024 | yes | yes | yes | yes | yes |
2023-24 | Advanced Encryption Standard (AES)(*) | SeSl | Region 8 | Benelux Section | 30 December 2023 | yes | yes | yes | yes | yes |
2024-22 | BELLMAC 32 Microprocessor | BBrg | Region 1 | North Jersey Section | 15 November 2024 | yes | yes | yes | yes | yes |
2024-25 | First Karaoke Machine, 1967(*) | TmHs | Region 10 | IEEE Tokyo Section | 29 October 2024 | yes | yes | yes | yes | yes |
2024-26 | Vacuum Fluorescent Display, 1967(*) | TmHs | Region 10 | IEEE Nagoya Section | 28 October 2024 | yes | yes | yes | yes | yes |
E. UNDER BOARD OF DIRECTORS ACTION
(The schedule for upcoming Board of Directors meetings can be found in the right hand column of http://www.ieee.org/about/corporate/board/index.html or at Upcoming Series )
E.1 PROPOSALS APPROVED BY HISTORY COMMITTEE; AWAITING CITATION CONFIRMATION FROM PROPOSER(S)
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 Independent Expert reviewers suggested? | Expected date of BoD action |
E.2 PROPOSALS APPROVED BY HISTORY COMMITTEE BEING ACTED UPON AT UPCOMING BOARD OF DIRECTORS MEETING(S) OR TELECONFERENCE(S)
Docket Number | Short Name | Advocate initials | Region | Sponsoring Org Unit | COMPLETE Proposal submitted Date | Section support letter received? | Site owner permission letter received? | Payment commitment received? | Full text of references received? | 4 Independent Expert Reviewers Suggested? | Expected date of BoD action |
2023-01 | University of Hawaii 2.2 meter Observatory | SrPo | Region 6 | Hawaii Section | 23 May 2024 | yes | yes | yes | yes | yes | 25 November 2024 |
2023-25 | Dynamic Single-Mode Semiconductor Laser | JnMz | Region 10 | Tokyo Section | 16 January 2024 | yes | yes | yes | yes | 25 November 2024 | |
2024-21 | Fast Fourier Transform (FFT) | BBrg | Region 1 | Section Princeton/Central Jersey and New York Sections | 5 September 2024 | yes | yes | yes | yes | yes | 25 November 2024 |
F. FINAL APPROVAL GIVEN
F. DEDICATIONS BEING PLANNED, ALL APPROVALS HAVING BEEN RECEIVED
Docket Number | Short Name | Region | Sponsoring Org Unit | Dedication Date | Dedication Ceremony Info | |
2013-22 | Introduction of Apple II Computer | EiJh | 6 | Santa Clara Valley Section | postponed from 2 May 2020 | |
2013-28 | Introduction of Apple I Computer | EiJh | 6 | Santa Clara Valley Section | postponed from 2 May 2020 | |
2014-06 | Macintosh Computer, 1984 | JhIp & DvMc | 6 | Santa Clara Valley Section | Postponed from 2 May 2020 | |
2017-09 | Itaipu Hydroelectric Power Plant, 1984 | ErTj | Region 9 | Paraguay Section | ||
2019-09 | URUCIB Presidential Information System, 1988 | SrPo | Region 9 | Uruguay Section | 4 December 2024 | |
2020-01 | Experimental Radio Station XWA, 1919 | DvBr | Region 7 | Montreal Section | 6 May 2025 | |
2020-04 | Intel 4004 Microprocessor | DvBr | Region 6 | Santa Clara Valley section | TBD | |
2020-07 | Universal Serial Bus (USB) | DvBr | Region 6 | Oregon Section | TBD | |
2021-01 | Commercialization of the Fishfinder, 1948 | TmHs | Region 10 | Kansai Section | 25 April 2025 | |
2021-20 | Long-Distance Transmission of Three-Phase Alternating Current, 1891 (*) | IaPc | Region 8 | Germany Section and Poland Section | possibly March 2025 | |
2021-21 | Pulse Oximetry (*) | AtSv | Region 10 | Tokyo Section | 14 November 2024 | |
2022-19 | Toyota Prius | TmHs | Region 10 | Nagoya Section | 30 October 2024 | |
2022-22 | Intel 8087 Math Coprocessor | BBrg | Region 8 | Israel Section | Postponed from September 2024 | |
2023-05 | Anderson Bridge (*) | AtSv | Region 8 | UKI Section | ||
2023-06 | Project Echo | DvBr | Region 1 | New Jersey Coast Section | 17 May 2025 | |
2023-09 | Cobalt-60 Radiation Cancer Treatment, 1951 | DvMc | Region 7 | London section, North Saskatchewan Section | ||
2023-20 | Heavy Ion Accelerator Facility, 1973 | BBrg | Region 10 | Australian Capital Territory Section | 26 February 2025 | |
2023-28 | TRON Intelligent House, 1989 | TmHs | Region 10 | Tokyo Section | 28 November 2024 | |
2023-29 | Laser Ionization Mass Spectrometer, 1988 (*) | TmHs | Region 10 | Kansai Section | 15 November 2024 | |
2024-06 | Integrated Circuits for Satellite Digital Radio, 1996-1997 | KiMo | Region 8 | France Section, Italy Section | ||
2024-16 | First Electrostatic Generator in Japan, 1776(*) | TmHs | Region 10 | Shikoku Section |
G. DEDICATIONS HELD
For a list by dedication date of all IEEE Milestones dedicated from the beginning of the Milestone Program, see https://ethw.org/Milestones:List_of_Milestones#Milestones_By_Year_Dedicated_And_Region